Who is responsible for authorizing changes to high pressure piping anchors, guides, and expansion joints?

  1. The professional engineer

  2. A licensed plumber

  3. The facility manager

  4. An inspector

The correct answer is: The professional engineer

The professional engineer is responsible for authorizing changes to high pressure piping anchors, guides, and expansion joints because this role requires a comprehensive understanding of engineering principles, safety standards, and system design. Such changes can heavily impact the integrity and functionality of the entire piping system, necessitating the expertise that only a professional engineer possesses. The involvement of a professional engineer ensures that any modifications comply with applicable codes and regulations, maintaining the safety and efficiency of the system. Changes to anchors, guides, and expansion joints can alter how the system handles stress and temperature fluctuations, which are critical factors in high-pressure environments. Thus, only someone with the appropriate qualifications and understanding of mechanical engineering and system dynamics should authorize such modifications.